Al Tayer Chairs Dubai Metro Blue Line Forum meeting at Tunnel Rings Production Factory in International City
Last Update: Wednesday, December 17, 2025 : 12:02 (+4GMT)
- Two ready-mix concrete batching plants and two precast concrete production sites established in Al Ruwayyah 3 and International City
- 3,500 engineers and workers deployed across 12 sites to deliver the project by 9.9.2029
Dubai. Roads and Transport Authority. 17th December 2025:
His Excellency Mattar Al Tayer, Director General, Chairman of the Board of Executive Directors of the Roads and Transport Authority (RTA) chaired the Dubai Metro Blue Line Forum meeting at the Precast Concrete Production and Storage Factory in International City, attended by the heads of the Dubai Metro Blue Line Project Consortium. The meeting brought together the chairmen of the boards of MAPA, Limak, and CRRC Hong Kong, the heads of the consultancy and contracting companies delivering the project, as well as several RTA CEOs.
The Forum convenes on a regular basis as part of RTA’s strategy to monitor progress and take the necessary decisions to ensure compliance with the approved project schedule.
During the meeting, the Forum reviewed project updates and progress. More than 3,000 workers are currently engaged on the project under the supervision of 500 engineers and specialists, distributed across 12 locations. The consortium has completed over 4.6 million working hours across the various construction sites, while overall project completion has reached 12%. The project team expects progress to rise to 30% by the end of 2026, with the project set to open in line with the approved programme on 9.9.2029.
Concrete Casting Plant
Al Tayer and members of the Forum Meeting inspected the ready-mix concrete casting plant. Additionally, Dubai Metro Blue Line represents the first rail project implemented by RTA to include two ready-mix concrete batching plants and two precast concrete storage facilities in Al Ruwayyah 3 and International City. This approach reflects RTA’s proactive delivery of major projects, strengthens quality assurance and efficiency of construction materials, ensures full control over manufacturing and supply chains, reduces implementation timelines, and enhances the efficiency of logistics operations.
Al Tayer and members of the Forum Meeting received a briefing on the production capacity of the two plants. The ready-mix concrete batching plant in Al Ruwayyah 3 produces 200 cubic metres of ready-mix concrete, while the viaduct precast production yard delivers between 10 and 12 viaduct segments per day. In International City, the ready-mix concrete batching plant produces 120 cubic metres of ready-mix concrete, and the precast tunnel rings factory produces 12 rings per day.
Dubai Metro Blue Line spans 30 km and includes 14 stations, making it one of RTA’s key strategic projects. The line links the Red and Green Lines of Dubai Metro and serves areas with an estimated population of around one million by 2040. It provides direct journeys to Dubai International Airport in 20 minutes and supports the objectives of the Dubai 2040 Urban Master Plan by connecting the fifth urban area to the metro network, enhancing quality of life for residents and visitors, and realising the 20-minute city concept by enabling access to more than 80% of services within 20 minutes of travel. The project also supports Transit-Oriented Development (TOD), advances the Dubai Economic Agenda (D33), increases land and property values around stations by up to 25%, and reduces traffic congestion by 20% on the corridors served by the Blue Line.
Captions:
- Part of the Forum Meeting of Dubai Metro Blue Line project
- Al Tayer and members of the Forum during their inspection of the tunnel rings production factory in International City
- Bridal Season Is Officialy Open with Benefit Cosmetics!... [2461-Views]
- Dubai Summer Surprises 2026 Unveils an Action-Packed Calendar of Shopping, Din... [2001-Views]
- Joyalukkas Strengthens US Footprint with 8th Showroom in Iselin, New Jersey... [1952-Views]
- Malabar Gold & Diamonds continues its expansion in North America: Launches 8th... [1808-Views]
- Mercato Takes Media on a Magical Summer Journey with The Grand Comedy Circus a... [1570-Views]
- Hamdan bin Zayed chairs 2nd Environment Agency – Abu Dhabi board meeting in 20... [1465-Views]
- Group-IB launches Purple Teaming service to close the gap between security inv... [1168-Views]
- First winner of 'Win Your Home in Dubai' initiative announced as citywide home... [1118-Views]
- Dubai Gears Up for a Spectacular Start to 29th Dubai Summer Surprises with Liv... [1077-Views]
- Government of Fujairah Signs Agreement to Purchase Gasoline Production from Et... [947-Views]
- Global Talent Attraction and Retention Committee Convenes Tenth Meeting to Rev... [915-Views]
- MAIR Group and Makani Real Estate Announce Mall of Al Ain Redevelopment and Ex... [888-Views]
- Schneider Electric joins the World Economic Forum Lighthouse Operating System ... [885-Views]
- EGA wins the AI Vision and Strategy Award at the 2026 Manufacturing Leadership... [878-Views]
- EGA inaugurates UAE's largest aluminium recycling plant... [825-Views]
- Kia introduces PV5 as its first Platform Beyond Vehicle (PBV) model in Middle ... [819-Views]
- G-SHOCK MTG-B4000BD-1A: A New Language of Structural Beauty... [812-Views]
- The New SHEGLAM Lashlighter Root-Up Lash Primer Gets to the Root of the Matter... [797-Views]
- Dubai Summer Surprises: Shop, Save, and Win as the Great Dubai Summer Sale Arr... [797-Views]
- New economic licences in Abu Dhabi increase 21% in Q1 2026... [789-Views]